> »ç¾÷ºÐ¾ß > ´ã¼ö BG >
°ø±Þ½ÇÀû
Umm Al Nar Desalination Station ¡®B¡¯
- The shortest time span of delivery : 12 months after contract
Client : Abu Dhabi Water & Electricity
Authority
Capacity : 62.5 MIGD Desal
Scope : EPC
Period : Jul. ¡¯00 ~ Dec. ¡¯02
Location : Abu Dhabi, UAE
Status : Completion (¡¯02.8)
¢Ã Completed Project